IES was a foundational supplier for the Rewa Ultra Mega Solar Park (750 MW), providing the structural backbone for one of the world's largest single-site solar installations. This project marks a significant milestone in India's transition to renewable energy.

Client
Rewa Ultra Mega Solar Ltd
EPC Partner
Sterling & Wilson
Location
Madhya Pradesh
Duration
14 months
Year
2021

The Challenge

The vast, undulating desert terrain of Rewa required module mounting structures (MMS) that could be quickly adapted to varying pile heights while maintaining perfect solar alignment. Furthermore, the structures needed to withstand peak wind gusts of up to 170 km/h as per revised Indian wind load standards.

Our Solution

We deployed a high-precision fabrication line for C-channel rafters and purlins, using automated punching to ensure millimetre accuracy for module mounting. IES supplied heavy-duty hot-dip galvanized steel with optimized hole patterns that allowed for rapid field assembly, significantly accelerating the EPC timeline.

Products Supplied

High-Precision C-Channel Purlins & Rafters
HDG Solar Module Mounting Frames
Heavy-Gauge Ground-Mount Pile Foundations
Chemical Earthing Kits for Solar Parks

Results & Impact

Successfully supplied structural mounting for a 250 MW project block
Validated structural integrity against 170 km/h peak wind load audits
Maintained a high-volume delivery rate of 500 tons per week