EMAIL:info@cabletray.net
LIVE PRODUCTION
NRSS XXIX Transmission Project
Transmission2021Completed

NRSS XXIX Transmission Project

Critical infrastructure supply for the Northern Region Strengthening Scheme, providing reliable power to the Kashmir valley.

Client
Sterlite Power
EPC Partner
KEC International
Location
Jammu & Kashmir
Duration
18 months
Year
2021

The Challenge

Extreme climate (snow/ice) and strategic security concerns. Earthing materials required high durability against soil acidity and freeze-thaw cycles.

Our Solution

Supplied copper-bonded steel earth rods with thick 254-micron molecular coating and high-strength galvanized lattice supports.

Products Supplied

Copper-Bonded Earth Rods
High-Strength Lattice Supports
GI Earthing Flats
Tower Foundation Earthing

Results & Impact

Enabled stable power for 3 million people
Zero grounding failures in extreme winter
Phased supply through difficult terrain
Commendation received for supply reliability